Fluor booked the undisclosed contract value in 3Q18.

Fluor’s scope includes design, procurement, construction and commissioning support for the new 45 mega volt amps natural gas-fired combustion turbine generator system that will supply power and steam to enhance the refinery’s energy efficiency and operations. The scope also includes substations, transformers, electrical and piping tie-ins and a fuel gas pipeline system.

The project, the first to receive planning permission as a Development of National Significance process under the Planning (Wales) Act 2015, will be executed on a cost reimbursable basis by an integrated engineering team located at Fluor’s office in Farnborough, UK and at the Pembroke Refinery.