Located on the west side of the Calcasieu Ship Channel, near the entrance to the Gulf of Mexico, the project will include six LNG storage tanks each with a capacity of 40 000 m3, one marine loading berth capable of loading LNG carriers up to a capacity of 216 000 m3, and a 3.04 mile long, 30 in. dia. pipeline that will connect the LNG facility with existing intrastate and interstate pipelines for the purpose of supplying gas to the project.

“We are very pleased to receive FERC’s Issuance of Notice of Schedule for Environmental Review. It confirms that our project remains on schedule to take FID in 1Q21 and start commercial operations in 1Q24”, said Paul Varello, Commonwealth LNG’s President and CEO.